Live build · Summit Ridge Custom Homes

Pardoe Residence

Alpine, Utah · 1.6 acres · east bench, Box Elder Peak views

8,400 sq ft · 6 bed · 8 bath · sport court + pool

Overall progress

7%

Current phase

Excavation & Foundation

Schedule

On schedule

Target move-in

Fall 2027

Broke ground June 2026Next: Footings poured & inspected · Jul 10, 2026

This week, in plain English

Week of June 29 – July 2

Generated Wednesday, Jul 2 · from 24 site photos, 4 daily logs, and the master schedule

Footings are formed on the walkout level and rebar is being tied ahead of the pour, which is scheduled for Wednesday, July 8 with the city inspection two days later. The over-dig on the northeast corner was backfilled and compacted after the engineered retaining upgrade was approved last week. One thing needs your eyes: the window package decision is due July 17 — it carries a 16-week lead time, which is what protects the framing start in September.

Foundation 18% → 30%24 photos addedPour: Jul 8 · Inspection: Jul 10

Week of June 22–27

Generated Sunday, Jun 27

The dig finished Tuesday — about 2,100 yards of material out, most staged on-site for backfill. The soils engineer signed off on bearing at depth on Thursday. The northeast corner needed an engineered retaining upgrade at the walkout; the change order came in at $18,400 and was approved from the app the same day.

Excavation complete31 photos addedCO-1 approved · $18,400

Week of June 15–20

Generated Sunday, Jun 20

Ground broke Monday morning. The lot was cleared and staked, erosion control went in, and the excavator started the main dig Wednesday. Temporary power was set Friday. Alpine City closed out the last permit condition — nothing outstanding on the paperwork side.

Groundbreaking Jun 1519 photos added0 open permit conditions

Needs you · 3 open

Every selection is tied to a real lead time, so due dates mean something. Decide here and the builder is notified instantly.

Window & door package

Due Jul 17

Sierra Pacific vs. Andersen E-Series. 16-week lead time — must be ordered before framing starts to avoid a shell-phase stall.

Exterior stone blend

Due Aug 21

Three blends sampled at the design center. 5-week lead time; mason is penciled in right after shell.

Roof material & accent color

Due Aug 28

Standing-seam metal accents over architectural shingle. Locks the shell-phase order.

Recently decided

Foundation waterproofing: Full membrane + drain board · Jun 24Walkout patio footprint: Extended 6' for outdoor kitchen · Jun 18Sport court placement: NE corner, sunk 4' · May 22

The whole build, at a glance

  1. Design & Engineering

    Nov 2025 – Apr 2026
  2. Permits & Site Prep

    Apr – Jun 2026

    Alpine City permit issued Jun 9. Lot cleared and staked Jun 15.

  3. 3

    Excavation & FoundationIn progress · 30%

    Jun – Sep 2026

    Dig complete on the walkout level. Footings formed this week — pour scheduled Jul 8, inspection Jul 10.

  4. 4

    Framing

    Sep – Dec 2026

    Lumber package bids due back Jul 24.

  5. 5

    Roof & Exterior Shell

    Dec 2026 – Feb 2027
  6. 6

    Mechanical Rough-Ins

    Jan – Apr 2027
  7. 7

    Insulation & Drywall

    Mar – May 2027
  8. 8

    Interior Finishes

    May – Sep 2027
  9. 9

    Flatwork, Pool & Landscape

    Jul – Oct 2027
  10. 10

    Punch List & Final Walkthrough

    Oct – Nov 2027

The design

Fieldstone Architecture · Construction set Rev C · Jun 2

South elevation at dusk

Great room glazing toward Box Elder Peak

Concept

Entry court, first snow

Board-formed concrete and cedar at the approach

Concept

Pool terrace & sport court

Walkout level opening to the east lawn

Concept

Great room, morning

24-foot ceilings, steel-framed fireplace wall

Concept

Concept art shown — the architect’s renderings drop in here.

Material palette

Montana moss rockBoard-formed concreteRift-sawn white oakBlackened steelStanding-seam zincWestern red cedar

Floor plans

8,400 sq ft across three levels

Site Plan

1.6 acres

Rev C · Jun 2

  • East-bench orientation
  • Gated auto court
  • Pool + sport court, east lawn

Main Level

3,150 sq ft

Rev C · Jun 2

  • Great room, 24' ceilings
  • Chef + back kitchen
  • Primary wing with peak views

Upper Level

2,050 sq ft

Rev B · May 14

  • Three en-suite bedrooms
  • Loft lounge over great room
  • Upper laundry

Walkout Lower Level

3,200 sq ft

Rev C · Jun 2

  • Theater + golf simulator
  • Gym with cold plunge
  • Guest suite, pool access

The budget, with nothing hidden

Contract

$4,600,000

Approved changes

+$18,400

Current total

$4,618,400

Paid to date

$322,000

Change orders

  • Walkout retaining wall — engineered upgrade

    Approved Jun 26

    +$18,400
  • Heated driveway loop extension

    Pending your approval

    +$22,600

Draw schedule

  • Deposit · Contract signing

    Paid Apr 30

    $230,000
  • Draw 1 · Permit + mobilization

    Paid Jun 12

    $92,000
  • Draw 2 · Foundation complete

    Due ~Sep 4

    $386,000

Contingency used: 4% — healthy for this stage of the build.

From the site

Placeholder tiles — real job photos drop in here

Footings formed, walkout level

Jul 1

Rebar tied — northeast corner

Jul 2

Dig complete, from the ridge

Jun 23

Soils engineer on site

Jun 25

First bucket — groundbreaking

Jun 15

Lot staked, Box Elder Peak behind

Jun 12

The vault

Placeholder files — originals drop in when the builder connects

Every contract, permit, and stamped drawing for the house — in one place, forever. No more “can you resend that PDF.”

Contracts & Agreements

  • PDF

    Construction Agreement — executed

    Apr 30 · 4.2 MB

  • PDF

    Architectural Services Agreement

    Nov 12 · 1.8 MB

  • PDF

    Allowance Schedule — Exhibit B

    Apr 30 · 640 KB

Permits & Approvals

  • PDF

    Alpine City Building Permit #26-0417

    Jun 9 · 890 KB

  • PDF

    Geotechnical / Soils Report

    Feb 3 · 12.4 MB

  • PDF

    Grading & Erosion Control Approval

    Jun 4 · 1.1 MB

Plans & Engineering

  • PDF

    Construction Set — Rev C (full)

    Jun 2 · 48 MB

  • PDF

    Structural Calculations

    May 20 · 9.6 MB

  • PDF

    Truss Package — shop drawings

    Jun 27 · 7.2 MB

Insurance & Compliance

  • PDF

    Builder's Risk Certificate

    May 1 · 310 KB

  • PDF

    GC Liability + Workers' Comp Certs

    May 1 · 420 KB